REPAIR OF ROOF STRUCTURE AND RENNOVATION OF TOILETS AT THE ASEAN FOUNDATION

Deadline: 2018-05-31

REQUEST FOR PROPOSAL

REPAIR OF ROOF STRUCTURE AND RENNOVATION OF TOILETS AT THE ASEAN FOUNDATION

  1. BACKGROUND

Three decades after ASEAN was established, ASEAN leaders recognized that: there remained inadequate shared prosperity, ASEAN awareness and contact among people of ASEAN. It was of this concern that ASEAN leaders established the ASEAN Foundation during ASEAN’s 30th Anniversary Summit in Kuala Lumpur Malaysia on 15 December 1997. The ASEAN Foundation is an organisation from and for the people of ASEAN and exists because of one vision: to build a cohesive and prosperous ASEAN Community. As an ASEAN’s body, the Foundation is tasked to support ASEAN mainly in promoting awareness, identity, interaction and development of the people of ASEAN. For more information, visit: https://www.aseanfoundation.org

  1. OBJECTIVES OF THE ASSIGNMENT

The ASEAN Foundation would like to invite reputable companies in Jakarta to facilitate repairs and maintenance of the roof structures of the ASEAN building in Jakarta, renovate its toilets and to paint the exterior and interior walls of the building. The works are done in order to preserve the building life span and to ensure compliance to occupational health and safety as well as legislative requirements.

The ASEAN Foundation is located on Jalan Sam Ratulangi, No 2, Menteng, Jakarta 10350. GPS Coordinates are: Latitude: -6.187686 Longitude: 106.832883

  1. SCOPE OF SERVICES

The ASEAN Foundation requires from appropriately qualified, competent, experience and professionally registered contractors to:

a) Roofing

  • Undertake the status analyses of the ASEAN Foundation roof structures

b) Toilets

  • Install new fixtures and tiles for the male, female, Executive Director’s and drivers’ toilets to include installation of a shower room

c) Interior and Exterior Walls

  • Apply new paint for interior and exterior walls of the building
  • Replaster exterior wall

d) Working Space for Eight People

  • Close up division in working space to make two separate entrances

e) Carpeting

  • Install carpeting for the Board of Trustee room

The contractor shall submit quotations for repairs and maintenance of roof structure and carry out the assignment as detailed above. The contractor shall ensure that its team has relevant expertise and have the necessary equipment and support to undertake the work. The contractor will be expected to issue the warranty of certificate on the work done.

  1. EXPECTED DELIVERABLES

4.1 Roofing

  • Waterproofing of roof to repair all leaks inn apex flashing, parapets, ridge capping’s, flat roofs, etc
  • Ensure that all securing bolts are still effective and correct defaults between sheets, roof capping and flashing to prevent any leakages
  • Check roofs for signs of corrosion and wire brush top bare metal and coat with a rust inhibitor
  • Apply two (2) coats of dark dolphin roof coating or equivalent to match existing
  • Replacement of rusted and damaged gutters and downpipes
  • Replacement of damaged or missing facia boards
  • All new materials used in repair work shall be approved equal quality, colours, profiles, thickness, etc. and shall in all cases match the existing materials and shall be fixed to existing materials or surfaces.

4.2 Renovation of Toilets

  • Install new fixtures and tiles for the male, female, Executive Director's, and drivers’ toilets to include installation of a shower room

4.3 Interior and Exterior Walls

  • Thoroughly clean and wash the existing painted wall surfaces before apply new paint for exterior walls of the building
  • Apply new of walls of common corridor areas and rooms
  • Replaster exterior wall

4.4 Working Space for Eight People

  • Close up division in working space to make two separate entrances

4.4 Carpeting

  • Install carpeting for the Board of Trustee room

  1. GENERAL

There will be a site inspection meeting on 25 May 2018, from 10.00 am to 17.00 pm at the ASEAN Foundation. Failure to attend will be an automatic disqualification.

It is important to note that the successful person will work under the supervision of an ASEAN Foundation representative and abide by its organisational guidelines.

6. SUBMISSION OF QUOTATIONS

Quotations should be submitted no later than 31 May 2018 to the following email address:

The Tender Committee

ASEAN Foundation

Jl Sam Ratulangi, No 2 Menteng

Jakarta 10350

Tel: 021 3192 4833

Quotations must be submitted in a sealed proposal, with two separate sealed envelopes:

  • Financial proposal
  • Technical proposal

Further information regarding technical matters can be sent an email to:

riza.olivia@aseanfoundation.org or at tel: 021 3192 4833

The selection of the qualifying proposal will be at the ASEAN Foundation’s sole discretion. The ASEAN Foundation does not bind itself to accept any particular bid/proposal, and the ASEAN Foundation reserves the right not to appoint the service provider.

  1. DURATION/TIME FRAME:

The contract is expected to start from 15 June to 31 August 2018 (tentative)

  1. QUOTATION FORMAT

No

Description Roof Structure

Unit

Qty

Unit Price (IDR)

Total Cost (IDR)

Remarks

A

WORKING PREPARATION

Mobilization

1

lot

-

Support tools

1

lot

-

Cleaning

1

lot

-

Sub total A

Sub total A

-

1

Roof Structure

1,1

Waterproofing of flat roof at XXX to prevent roof leaks – Darachem – Daraflex in conjunction with a membrane (or equivalent). To be applied as per manufacturer’s instructions.

250,5

m2

-

1,2

Checking, fastening and replacement of defected roof securing bolts and correcting excessive gaps between sheets, roof capping and flashing. The area of this work is 40% of total roof building

560

m2

-

1,3

Painting of roof sheeting with Darachem superroof coating or equivalent roof paint. Apply two coats. To be applied as per manufacturers instruction.

560

m2

-

Sub total 1

-

2

BACKSIDE WORKING

-

2,1

Unloading the roof

116,1

m'

-

2,2

Making existing stand pile

10

point

-

2,3

Unloading the ceiling

116,1

m'

-

2,4

Install the lightweight steel roof frame

116,1

m'

-

2,5

Attach the gutters of ex zincalume

27

ml

-

2,6

Install lisplang ex Zincalume

27

ml

-

2,7

Install the roof wx Zincalume 0.35 mm

116,1

m'

-

2,8

Install the gypsum ceiling

116,1

m'

-

2,9

Install lis ceiling

106

ml

-

2.10

Painting the ceiling

116,1

m'

-

2,11

Ex vinilex wall painting

267,9

m'

-

2,12

Roof painting

460

m'

-

2,13

Moving the door

1

Unit

-

Sub total 2

-

3

Gutters, Downpipes and Facia Boards

3,1

Unloading old gutters

30

ml

-

3,2

Install new gutters ex zincalume

30

ml

-

3,3

Install flashing tile

30

ml

-

3,4

Repaired the leaked ceiling

1

lot

-

3,5

Painting the walls look outside

800

m'

-

Sub total 3

-

4

Renovation of Female and Male Toilets

3,1

Unloading ceramic wall and floor

124,80

m2

-

3,2

Unloading closet

8

pcs

-

3,3

Install ceramic wall ex milan size 30 x 60 cm

154,56

m'

-

3,4

Install ceramic floor 30 x 30 cm

44

m'

-

3,5

Install the wall hebel

11

m'

-

3,6

Hebel wall plaster

25

m'

-

3,7

Floor drain

10

pcs

-

3,8

Tap Water

8

pcs

-

3,9

Install closet ex Toto + eco washer

8

pcs

-

3,10

Install washtafel ex Toto

5

pcs

-

3,11

Install urinal ex Toto

2

pcs

-

3,12

Install Mirror size 1 x 2,4 m

2

pcs

-

3,13

Install Partition for shower

2

pcs

-

3,14

Install Shower for bathroom

4

pcs

-

3,15

Repaint the door melamic

9

pcs

-

3,16

Install the gypsum ceiling

37,2

m'

-

3,17

Install ceiling tile

36

ml

-

3,18

Painting bathroom wall over ceramic

40

m'

-

3,19

Painting the ceiling

47

m'

-

Sub total 4

-

5

Exterior & Interior Walls

5,1

Apply paint over the existing cement paint surface including priming coat of exterior primer applied to give an even shade.

m2

206,9

-

5,2

Internal wall painting to achieve even shade and colour

m2

100

-

Sub total 5

-

6

Working Space for Eight People

6,1

Close up partition between rooms

m2

22

-

6,2

Construct an opening in the wall to build a doorway

lot

1

-

Sub total 6

-

7

Carpeting

7,1

Remove old carpeting in the Board of Trustees’ meeting room

m2

180

-

7,2

Install new carpet

m2

180

-

Sub total 7

-

TOTAL COST IN IDR

-